POLITICS

Coal recovery plan addresses imbalance in coal stock levels – Eskom

SOE says its overall stockpile level stands at 35 days excluding Medupi and Kusile

Eskom’s coal recovery plan addresses imbalance in coal stock levels

25 April 2018

The challenge of coal stock levels below the required target of 20 days at seven of our power stations is not ideal, more especially as Eskom prepares for the traditionally higher electricity usage period in winter. Eskom has, however, put measures in place to address the current coal shortages.

Eskom is highly cognisant of the significant impact insufficient coal supply would have on its operations and the entire country. The organisation is currently facing imbalances whereby several coal-fired power stations, particularly those in the Mpumalanga province are affected. However, it is also important to note that at this stage, the level of coal stock days in more than half of the 15 coal-fired power stations in the Eskom generation fleet is maintained above the grid code target of 20.

The prevailing situation at seven stations Arnot, Tutuka, Majuba, Hendrina, Camden, Kriel and Komati power stations, is that coal stock levels are below the required target of 20 days as stipulated in the Grid Code.  Although the total current coal stock day levels of 35 days (excluding Medupi and Kusile Power Stations) are within an acceptable range it is necessary to have all stations at the required stock day levels.

A number of factors, including the historical underinvestment at cost-plus mines due to capital constraints and the undersupply on both coal quality and quantity by the Tegeta mines which are under business rescue, have negatively impacted stock levels and production. Eskom has informed Nersa of the current coal supply challenges and planned remedial actions as per regulatory requirements.

The recovery plan includes securing additional coal supplies for the affected stations and a further redirection of coal stock is underway to address the imbalance.

“The recent media reports on impending load shedding due to a shortage of coal are unfounded. Eskom has contracted 84% of the coal it requires over the next five years.  A recovery plan is in place to address the short-term imbalance of coal and to improve the stock days at the seven stations below minimum. Eskom is working on ways to expedite the coal procurement process at these mines,” said Eskom’s Interim Group Chief Executive, Mr Phakamani Hadebe.

The situation cannot be compared to 2008 when we experienced load shedding. During that period coal production and delivery were severely affected with wet coal – due to abnormal rain fall – being at the centre of the various challenges experienced at that time. On top of those challenges, was an increase in demand for electricity which resulted in coal stockpile levels being significantly lower than the targeted levels. In the first week of January 2008, the number of stockpile days was at an average of 12 days and improved to 24 days in July 2008.

Currently Eskom’s overall stockpiles level is at 35 days excluding Medupi and Kusile. Furthermore, the additional capacity from our new build power stations, has increased capacity further enabling us to keep the lights on.

It remains standard practice at Eskom to increase vigilance on all critical processes particularly during the traditionally higher demand winter period in order to manage for the unexpected and to ensure that the lights stay on.Management of the coal stock levels is undertaken daily and forms part of the generation production plan that takes into account the planned repairs and maintenance needed at some stations along with prioritisation of stations burn rate.

The challenge of coal stock levels below the required target of 20 days at seven of our power stations is not ideal, more especially as the organisation prepares for the traditionally higher energy usage period in winter. We have however put measures in place to mitigate the situation and if the current state does not improve, we will meticulously reassess the situation, review our plans and take the necessary action.

Issued by Eskom Media Desk, 25 April 2018