STATEMENT BY THE EXECUTIVE MAYOR, ALDERMAN PATRICIA DE LILLE
RR informal settlement will be electrified in January 2012
The City of Cape Town and Eskom have resolved the two year impasse with the community of RR Section informal settlement over the relocation of a number of households which were blocking the completion and commissioning of the Esethu substation in Khayelitsha.
The agreement to relocate the families to Bardale - where they will have access to basic services, including electricity - has enabled Eskom to start upgrading the existing infrastructure in preparation for the actual electrification of the area early in 2012.
The commissioning of the Esethu substation will see more than 40 000 households gain access to electricity and will boost power supply to the whole of Khayelitsha. The provision of electricity in the area will go a long way towards improving the living conditions of the people in RR Section, many of whom will have electricity in their own households for the first time in their lives.
Eskom has undertaken to work through the festive holidays to ensure that all of the necessary groundwork for the electrification of the area is concluded on time to allow their contractors to lay cables when they return from their holidays.