POLITICS

Transformer suppliers appointed to connect new generation capacity – Eskom

Envisaged 101 large-scale and various other sizes of transformers will be required for infrastructure build rollout

Eskom appoints transformer suppliers for Transmission Development Plan to connect new generation capacity aligned with renewed localisation approach

24 June 2024

Eskom today announced the panel of transformer suppliers who will compete for upcoming transformer contracts to unlock the grid and ensure access to reliable electricity transmission across the country. Over the next 10 years, it is envisaged 101 large-scale and various other sizes of transformers will be required for the infrastructure build rollout.

The contracts are expected to be worth in the region of R7 billion over a period of four years.

“The aim is to connect 53GW of new generation capacity over the next ten years and to achieve this, innovative project delivery models and partnerships are being explored and implemented to drive accelerated delivery of the Transmission Development Plan (TDP), including a priority programme for strategic projects,” stated Segomoco Scheppers, Eskom’s Managing Director for Transmission.

The National Transmission Company of South Africa (NTCSA) issued an open tender enquiry on the 14th of March 2023 and five suppliers have successfully been selected to manufacture the power transformers to supplement the limited available local supply capacity.  Most suppliers are local with an international footprint.

The current schedule requires a first batch of 26 large scale transformers to be delivered between 12 to 36 months from order placement to meet the urgent requirement to increase transmission capacity for customers as well as independent power producers in order to contribute to overall economic growth.

Localisation strategy

The NTCSA has designed a framework agreement to procure the 101 large scale and various other sizes of transformers from the selected suppliers to address the large-scale demand up to the end of the 2028 financial year.  The suppliers will compete for various tenders over the coming years and the first batch of 26 power transformers has been issued to the suppliers and is expected to be awarded by July 2024.

The contracting strategy has been designed to allow for efficient procurement processes to maintain and strengthen governance and reduce lead times to adequately deliver on the TDP requirements, promote localisation and enable the delivery of approximately 28GW to the grid by the end of the 2028 Financial Year. The procurement will enable the NTCSA to meet its transformer needs across the country.

Subsequent tenders will encourage increasing local manufacture as the supply chain becomes more established in South Africa. An initiative to accredit more companies both locally and internationally has resulted in the NTCSA already accrediting 22 factories for various classes of transformers.

TDP Priority Programme

The transformer contract includes a list of 34 transformers that form part of two priority programmes to accelerate the delivery of the transmission infrastructure.  Firstly, 25 projects at existing substations will provide additional transformers to unlock 13 000MW of new generation capacity. Secondly, 22 expedited transmission projects will unlock 24 000MW of grid connection capacity. In summary, NTCSA is developing 47 projects that have the potential to unlock 37 GW of grid connection capacity between 2025 and 2033. These projects are at different stages of implementation in terms of design, procurement, and construction.

The recently established NTCSA will be undertaking the largest infrastructure rollout programme since the inception of its predecessor, Eskom’s Transmission Division. The commitment is to deliver 170 transformers to bring on board 105 865 MVA transformer capacity and 14 218km of new transmission lines by 2032.

NTCSA will provide regular updates on these projects and initiatives.

Issued by Eskom Media Desk, 24 June 2024