Gauteng Health underspends R559m on capital assets
11 June 2018
The Gauteng Health Department failed to spend a whopping R559 million on capital assets in the last financial year which ended on 31 March, despite a huge need for new machinery and hospital buildings which are falling apart.
This was revealed at a meeting of the Gauteng Legislature’s Health Committee last week on Friday.
According to the Department’s Fourth Quarter report which covers the January to March 2018 period, only R1.564 billion (73%) was spent out of a total R2.123 billion budget for capital assets.
R443 million was underspent for machinery and equipment, and R115 million of the capital budget was not spent on buildings and other fixed structures.