DOCUMENTS

How Zuma's Nkandla R7,8m was calculated - Pravin Gordhan

Finance minister provides tables with figures of how the sum was arrived at

NATIONAL ASSEMBLY

QUESTION FOR WRITTEN REPLY

QUESTION NUMBER: 1720 [NW1970E]

DATE OF PUBLICATION: 26 AUGUST 2016

1720.     Mr N Singh (IFP) to ask the Minister of Finance:

Whether he will provide a breakdown and analysis reflecting exactly how the National Treasury arrived at a total figure of R7,8 million being the full amount due and owing by the President, Mr Jacob G Zuma, in respect of his contribution to costs for non-security upgrades at his private residence in Nkandla as ordered by the Constitutional Court; if not, why not; if so, what are the full relevant details?

NW1970E

REPLY:

The Court order 5 made it clear that the scope of enquiry was limited to five distinct facilities, referred to as “measures implemented” that were built at the President’s residence at Nkandla, namely the: Visitor Centre; Amphitheatre; Swimming pool; Cattle kraal; and Chicken run.

The information used is outlined in Table 1, followed by two separate site visits with appointed service providers.  The reports from the two service providers, who undertook site inspections, were moderated by the third party applying the applicable norms and standards within the construction industry.

The breakdown of costs as submitted to the Constitutional Court is as outlined in Table 2.  

Information used for costing purposes was extracted from these drawings, as in Table 1 below.

The full report was submitted to the Constitutional Court and was made public by the Court.

Table 1: Drawings obtained from public works which provided costing information

Drawing No.

Description

Comment

PMB 0909/121

Visitors’ Facility – plan elevations and sections

The drawing received was for a single storey building whereas a double storey building was built,

Building layout incorrect

No cross-sections received

Elevations received are incorrect as they are not reflective of what is built

PPA-W-017-E-01-04

Swimming pool – detail and sections

Pool layout correct

Screen walls, retaining walls and paving not reflective of what was built

PPA-W-017-C-01-02

Swimming pool – detail and sections

PPA-W-015-A-01-00

Amphitheatre details

-

PPA-W-008-B-01-01

Cattle kraal Concept

Cattle kraal layout not reflective of what was built

Unnumbered

Chicken run – Sectional Elevation

 

Unnumbered

Site Section AX

Landscape Architect's site plan not to scale Typical section through site provided indicative information

Unnumbered

Site Section BX


Table 2: Revised cost estimates following the moderation process


* Inclusive of professional fees

Issued by Parliament, 26 September 2016