Joburg hospital psychiatric ward delayed yet again after 11 years and 4 contractors
1 December 2019
The badly needed renovation of psychiatric ward at the Charlotte Maxeke Johannesburg Hospital is now due to be completed on 31 January next year after missing the latest promised deadline of 31 October.
This was revealed by Gauteng Health MEC Bandile Masuku in an oral reply to my questions in the Legislature last week.
Work on the ward started in February 2008 and was supposed to be finished in 2014, but three companies had to be fired and the fourth company could not provide needed mechanical equipment that had to be imported from France at an extra cost of R4 million.
Two years ago, then Health MEC Gwen Ramokgopa disclosed that the cost of the ward had tripled to R34 million and she promised that it would be finished in March 2018.