Eskom cancels supplier contract due to inferior coal
Tuesday, 28 March 2017: Following the strict monitoring of the coal quality of all its suppliers delivering coal to its Tutuka Power Station, Eskom has cancelled its contractual relationship with Just Coal CC, a majority supplier of coal to the power station, due its consistent supply of inferior coal.
Eskom discovered that Just Coal CC was consistently delivering inferior coal. After numerous site visits to the contracted collieries, it was determined that coal supplied to the Tutuka Power Station by Just Coal CC was not extracted from the contracted collieries.
“This is in breach of its contractual obligations to Eskom. The result is that Eskom is burning an unknown combustion characteristic coal resource at its Tutuka Power Station, potentially resulting in load losses,” reacted Matshela Koko, Interim Group Chief Executive.
Koko added that in an effort to resolve the issue, Eskom requested technical information such as mine layouts and in situ coal qualities from Just Coal CC. “The information provided did not adequately address Eskom's concerns.”
Stated Koko: “On 16 March 2017, we had placed Just Coal in breach of its contractual obligations and requested additional technical information. We then afforded them until 23 March 2017 to provide the technical information and remedy the breach and they failed to do so.”