Load shedding costs Mpumalanga between R49 and R69 million per day
13 September 2022
The ongoing load shedding caused by Eskom's reduced generation capacity is costing Mpumalanga between R49 and R69 million per stage per day. This gives one an idea of the extensive economic damage it has caused over the years.
In response to a question by the FF Plus, the MEC for Economic Development and Tourism, Mr Vusi Mkhatshwa, corroborated calculations by the Council for Scientific and Industrial Research (CSIR).
According to these calculations, stage 4 load shedding costs between R196 and R276 million per 24-hour cycle, or between R8,2 and R11,5 million per hour.
The basis used for the calculations is the number of hours of load shedding and the national cost of load shedding (R500 to R700 million) in 2021, which is then assigned to the various stages thereof.