City Power employee implicated in R44 million Hopefield Substation corruption dismissed
4 March 2019
A City Power employee was dismissed on Friday, 1 March 2019, after he was found guilty of misconduct and collusion with contractors including granting payment of invoices for work not done at Hopefield Substation.
The employee, a project manager, was suspended when City Power initiated the investigation into his involvement. He was found guilty of gross negligence in his duties, resulting in financial loss to the City of Johannesburg.
The contracted involved was awarded a tender of R44 million to manage and conduct repairs at the Hopefield Substation.
The same contractor, Setheo Engineering, also received R66 million to upgrade the Eldorado Park Substation. But work was never done.